This Old New House
I originally posted the pics of the house we took on the original tour in the order we took them. That isn’t, however, the order the various projects took place. Moreover, some of the projects were done concurrently, and some of them might have been finished before others, even though they might have been started after them. This is as near as I can come to giving an idea of what I did and when:
Don’t pay much attention to this list. I’m only just beginning to compile it.
- Cut up and remove carpeting
- Dumpster 15 May to 25 May 2003
- Begin demolition in laundry room June 2003 finished June 2003
- Begin general cleanup on master bedroom floor June 2003
- Begin demolition in kitchen May 2003 cabinets May 2004 done July 2004 casings August 2007
- Begin demolition in master bathroom
- Begin demolition in library May 2003 rocked/painted February 2005 carpet October trim July 2007
- Begin demolition in shop
- Tree falled September 2006
- Big tree removed October 2006
- Pantry started July 2006 Phase I done 2009 Phase II done August 2009
- Flooring back rooms September 2009
- Shed October 2010
- Replace shower valve in front bathroom December 2010
- Bookcase June 2011
- Shop lights December 2011
Project | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012
|
Carpet removal | April | | | | | | | | |
|
Utility room | April-May | | | | | | | | |
|
Master bedroom | May-June | | | | | | | | |
|
Master bath | May | January | | | | | | | |
|
Kitchen | May | July | | | | | | | |
|
Library | May | | October | | | | | | |
|
Shop | | | | | | | | | |
|